Cladding claims, collateral warranties, strict compliance with Building Regs & exclusions in pre-tender not incorporated into the contract
The claim
The proceedings concerned claims brought by the
claimant in relation to re-cladding and associated
remedial works to address fire safety and water ingress
issues in relation to the external wall construction of
three high rise residential tower blocks it owned in central
Manchester.
The parties involved
The claimant was LDC (Portfolio One) Limited (“LDC”).
LDC is the freeholder of three residential tower blocks
(“Property”), which it acquired from a company not
involved in the proceedings. The construction of the
Property dates back to 2007. The Property consists
of the three individual blocks located around a central
courtyard and is operated, by LDC, as university halls of
residence in Manchester.
The first defendant was George Downing Construction
Limited (“Downing”). Downing was employed pursuant
to a building contract (“Main Contract”) by a company
not involved in the proceedings.
The second defendant was European Sheeting
Limited (In Liquidation) (“ESL”). ESL was employed,
by Downing, as the specialist sub-contractor for the
external wall systems pursuant to a sub-contract (“Sub-
Contract”).
The contracts
In 2015, LDC obtained the benefit of two collateral
warranties which Downing and ESL had entered into in
respect of their respective obligations under the Main
Contract and Sub-Contract. LDC’s claims were brought
pursuant to those two warranties.
The Main Contract
The Main Contract, entered into in June 2007, took the
form of the JCT Standard Form of Building Contract
with Contractor’s Design 1998 Edition incorporating
Amendments 1 to 5 and further bespoke amendments.
So far as material:
- The Works were required to comply with, inter alia,
all Statutory Requirements, which included the
applicable Building Regulations. - The Employer’s Requirements (“ERs”) required the
provision, inter alia, of “all cavity barriers to meet the
requirements of the Building Regulations Approved
Document B”.
The Sub-Contract
The Sub-Contract, dated September 2008, took the form
of the JCT Standard Form of Sub-contract for Domestic
Sub-contractors (DOM/2, 1981 Edition, incorporating
Amendment 1 (1987), Amendments 2, 3, 4, 5 and 6
(1989) and Amendment 7 (1992) with further bespoke
amendments. So far as material: - ESL was deemed to have notice of all provisions in
the Main Contract save for detailed prices. - ESL was required to complete the Sub-Contract
works so that no act, omission or default would
give rise to a breach by Downing under the Main
Contract. - ESL was required to observe, perform and comply
with all the provisions of the Main Contract. - As to design, the Sub-Contract was in materially
similar terms to the Main Contract and required ESL
to exercise reasonable skill and care.
Case analysis:
LDC (Portfolio One) Limited v (1) George Downing
Construction Limited and (2) European Sheeting Limited
[2022] EWHC 3356 (TCC)
stopping; - the substitution of the SIPs with a new Steel Framing
System (“SFS”); - the reinstatement of the existing Cor-ten steel panels;
- the replacement of the composite cladding and
glazed panels; and - making good of internal areas affected by water leaks
or the remedial works themselves.
Prior to implementing the Permanent Remedial Scheme,
LDC carried out certain temporary remedial works
(“Temporary Remedial Works”) which: - were based on advice given by a firm of civil and
structural engineers that fixings which secured the
composite cladding to the buildings could fail due
to deterioration in the SIPs to which the fixings were
attached; and - involved bolting the composite cladding to the inner
leaf of the buildings which, in turn, re-fixed all the
SIPs on the composite cladding elevations to ensure
that they would not detach from the buildings.
Procedural background
In October 2022, about two weeks prior to the trial,
the legal proceedings between LDC and Downing were
settled on confidential terms. The settlement sum was
£17.65m (“Settlement Sum”).
Prior to that, in around May 2022, ESL entered into
a Creditors’ Voluntary Liquidation, following which it
played no further part in the proceedings (as part of the
litigation, it had served an amended defence in June
2021): ESL did not serve any witness statements or
expert reports and the proceedings took place in ESL’s
absence.
LDC and Downing sought to enter judgment against ESL
as follows: - LDC claimed £21.1m against ESL for:
o the cost of remedial works; and
o loss of income. - A Sub-Contract Document included the Architectural
Specification (“Spec”), which formed part of the ERs
under the Main Contract: in common with the ERs,
the Spec required the provision of cavity barriers.
The external wall systems
Each block was over 18 metres high with external wall
systems built as follows: - Block 1 had Cor-ten steel cladding (North, Each and
South elevations) and composite cladding (West
elevation); - Block 2 had composite cladding (North elevation)
and glazed panels (East, South and West Elevations);
and - Block 3 had composite cladding (all elevations).
Each external wall system contained a breather
membrane and Structural Insulated Panels (“SIPs”). The
SIPs were fixed to the structural concrete frame of each
block.
The problems that arose
Following water ingress issues and subsequent
investigations, it was discovered that: - defects to the external wall construction of the
cladding had led to water ingress and deterioration of
the SIPs; and - fire barrier and fire stopping issues existed between:
o the rear of the SIPs and the contrate slab to all
elevations; and
o the rear of the cladding panels and outer face of
the SIPs on the Cor-ten elevations.
The remedial schemes
In mid-2021, LDC implemented a permanent remedial
scheme (“Permanent Remedial Scheme”) which
involved: - the removal of the cladding on all elevations
(including the glazed panels); - the removal of the SIPs;
- the installation of proper fire barriers and fire
(2) Relevant Statutory Obligations
ESL argued that the Building Regulations provided
no more than guidance and only required “adequate”
residence to the spread of fire or the passage of
moisture.
The Court held that: - ESL’s argument could not help ESL where
photographs showed there had been extensive water
ingress and that the external wall systems did not
(according to the expert evidence) include ‘adequate’
measures to inhibit the spread of fire. - The experts agreed that the design and construction
of the external wall systems did not comply with the
Building Regulations and, in relation to fire safety, the
agreed non-compliances included:
o the absence of vertical fire barriers;
o the omission or poor installation of horizontal fire
barriers;
o the omission of fire stopping between the rear of
the SIP panels and the concrete slab;
o the use of Rockwool RW45A material for fire
stopping which was not suitable to provide an
effective fire barrier; and
o the omission and/or inadequate installation of fire
stopping between the SIPs - ESL had not presented any evidence to support its
contentions that what was provided was adequate. - The defects constituted breaches of the collateral
warranty given by ESL based on breaches of the
Sub-Contract (by reference to the Main Contract)
by reason of non-compliances with the Building
Regulations and the Spec.
(3) Temporary Remedial Works
LDC’s claim included the cost of carrying out and
completing the Temporary Remedial Works. ESL alleged
that LDC failed to mitigate its loss because: - LDC delayed in undertaking remedial works, with the
result that the water ingress issues worsened; and - Adopting LDC’s case (without making admissions as
to its own breaches), Downing claimed an indemnity
and/or contribution from ESL for the Settlement Sum.
LDC and Downing relied on expert evidence from experts
in the fields of architecture, fire engineering and quantity
surveying.
What did the Court decide?
(1) Scope of ESL’s obligations
ESL argued that: - it was not obliged to comply with the Main Contract;
and - by virtue of a term of the Sub-Contract, it would only
be liable for design matters if it failed to exercise
the reasonable skill and care to be expected of
a professional designer (according to ESL, this
trumped any strict obligation to comply with Building
Regulations); and - the Sub-Contract excluded the provision of fire
breaks because ESL’s tender stated that ESL had
‘not allowed’ for them (ESL said this was reiterated in
the minutes of a pre-selection meeting).
The Court held that: - In carrying out the Sub-Contract, ESL was required
to comply with the applicable Building Regulations:
o the Main Contract required an obligation
for the works to comply with “all Statutory
Requirements” (which included the Building
Regulations);
o in the Sub-Contract, the obligation on ESL
to exercise reasonable skill and care did not
supersede the obligation to ensure that Downing
was not placed in breach of its obligations under
the Main Contract; and
o there was nothing to suggest that ESL’s skill and
care obligation should take precedence over
the strict obligation to comply with the Statutory
Requirements. - ESL’s tender was superseded by the Sub-Contract
and the statement in the minutes did not detract from
the detailed requirements of the Spec.
SIPs could not be replaced like-for-like because they
would not comply with the revised Building Regulations
2010 (as amended) and Regulation 7(2).
(5) Quantum
The quantum experts for each of LDC and Downing
valued the Temporary Remedial Works at £16.485m
and the Permanent Remedial Solution £16.430m. They
ultimately agreed on a figure of £16.457m, which the
Court accepted.
The Court also accepted LDC’s full claim for loss of rent
and the cost of having to decant the University students
whilst the remedial works took place. In the absence of
expert evidence from ESL, the claim of £4.694m was fully
accepted by the Court.
(6) Downing’s contribution claim against ESL
The Court held that Downing was entitled to a
contribution from ESL on the basis that ESL had agreed
to “indemnify and save harmless [Downing] from”
Downing’s liability to LDC arising out of ESL’s breaches
of the Sub-Contract and non-observance of the terms of
the Main Contract.
Finally, the Court held that the settlement was objectively
reasonable, in line with the judgment of Edwards-Stuart
J in Fluor v Shanghai Zhenhua Heavy Industry Co Ltd
[2018] EWHC 1 (TCC) at 465.
Implications for fire safety cases
The latest TCC judgment is relevant to fire safety cases
because it deals with a number of arguments that are
commonly deployed:
(1) In common with Martlet, the Court rejected the
proposition that: - ESL did not have an obligation to comply with
Building Regulations; and - that this was trumped by an obligation to
exercise reasonable care and skill.
(2) The Court dismissed ESL’s argument that the
guidance in the Approved Documents to the Building
Regulations required only ‘adequate’ resistance
to fire spread and water ingress. Not only did
ESL’s argument lack supporting expert evidence
but the Court was persuaded by photographic - the Temporary Remedial Works were unreasonable
because the insertion of coach bolts into the
composite cladding meant that it was impossible to
re-use the SIPs.
In relation to the alleged delay, the Court held: - LDC had taken steps to investigate and address
the issue of water ingress following receipt of a
report from a curtain walling specialist. There was a
period when more could have been done to advance
investigations and remedial works. However, there
was no evidence to suggest that delays during that
period impacted the scope of the remedial works. - ESL had undertaken various remedial works and
claimed that the issues had been resolved. However,
the issues were not resolved and ESL’s failure was a
significant cause of the deterioration.
In relation to the nature of the Temporary Remedial
Works themselves, the Court held that the works carried
out were not unreasonable: - taking immediate steps to undertake emergency
repairs in order to prevent a failure that would have
been a significant hazard was the right action for
LDC to have undertaken; - ESL had failed to suggest an alternative remedial
solution, such that there was no basis for a
conclusion that the works were unreasonable; and - the architectural experts considered that the
Temporary Remedial Works were reasonable as
they provided an immediate failsafe solution to an
unacceptable risk.
The Court concluded that there was no basis for
concluding that the Temporary Remedial Works were
unreasonable or that LDC had otherwise failed to
mitigate its loss in relation to those works.
(4) Permanent Remedial Works
ESL alleged that the Permanent Remedial Scheme was
one means of rectifying the fire safety defects, but it did
not advance an alternative remedial solution.
The Court concluded that LDC acted reasonably in
implementing the Permanent Remedial Scheme, which
was based on expert advice. Interestingly, LDC’s fire
engineering expert’s evidence was accepted that the - Without the collateral warranties, LDC would
have lacked the contractual nexus required to
pursue its claim. However, by reason of the
Building Safety Act 2022, it is possible that LDC
might have taken the benefit of the extended
limitation period under the Defective Premises
Act 1972. - The judgment also highlights the importance
of having a copy of the underlying contract
documents (in this case, the Main Contract
and Sub-Contract) to enable the claims to be
prosecuted effectively.
(3) The ease with which the contractual terms of a
superior agreement can be passed down to a sub-
contract – in this case, from the Main Contract down
to the Sub-Contract. As the terms in question were
not unusual, sub-contractors need to be mindful
of this point and ensure they properly review and
understand the terms of all of their sub-contracts and
associated risks.
(4) Claims that certain items of work were ‘not allowed’
in the tender/ excluded by some other document
(in this case, the minutes of a meeting). In time and
money claims, it is not uncommon for such a stance
to be taken: in the present case, the item allegedly
‘not allowed’ was fire barriers. The TCC dismissed
the argument on the grounds that the tender was
superseded by the Sub-Contract (ESL’s argument
was also contrary to the Spec). The case is however
insightful as to the Court’s approach.
For further information, please contact Matthew
Cocklin, Partner in our Construction team.
evidence and the expert evidence as to the defects.
Taken together, this showed that what was built
included fire and water resistance that was far from
‘adequate’.
(3) The Court dismissed ESL’s arguments that the
Temporary Remedial Works and the Permanent
Remedial Scheme were unreasonable: - Given that the freeholder, LDC, was required
to act in an emergency situation to address
a significant hazard, the Court was not open
to criticising the freeholder’s approach to the
Temporary Remedial Works. - In circumstances where the Permanent Remedial
Scheme was based on expert advice and ESL
had not put forward any alternative remedial
solution, the Court determined that the scheme
was reasonable. - Insofar as the freeholder had put the Permanent
Remedial Scheme in place, which complied with
the post-Grenfell amended Building Regulations
2010, the Court did not treat this as betterment.
Other take-away points
The decision also highlights a number of noteworthy
points:
(1) The importance of obtaining input from experts: - The Court accepted the evidence of the
independent experts in the fields of architecture,
fire engineering and quantum. As ESL did not
provide expert evidence, the Court accepted the
evidence presented by LDC and Downing. - The Temporary Remedial Works and Permanent
Remedial Scheme were based on the advice of
construction professionals. The Court therefore
accepted that LDC’s approach to the remedial
works was reasonable.
(2) The intrinsic value of a collateral warranty for
employers, purchasers, tenants and funders. This
is because the claim brought by LDC was one made
pursuant to the terms of a collateral warranty:
Matthew Cocklin
Partner
020 7065 1813
matthew.cocklin@devonshires.co.uk
www.devonshires.com 020 7628 7576
Devonshires has taken all reasonable precautions to
ensure that information contained in this document is
materially accurate however this document is not intended
to be legally comprehensive and therefore no action
should be taken on matters covered in this document
without taking full legal advice.
This article was originally written and published on the internet by Devonshires
This document (and any information accessed through links in this document) is provided for information purposes only and does not constitute legal advice. Professional legal advice should be obtained before taking or refraining from any action as a result of the contents of this document.
BDAS specialise in: providing contract advice, resolving construction disputes, managing construction claims & adjudications and will give you competitive, independent advice tailored to your specific construction problems.
If you could benefit from this please call Jon now on 07795 231 231 or email: Enquiry@BDAS.co
