L&AD’s & partial possession, general damages if unenforceable & capped at level of L&AD’s.

Claim No: HT-2020-000392
IN THE HIGH COURT OF JUSTICE
BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES
TECHNOLOGY AND CONSTRUCTION COURT (QBD)
[2021] EWHC 2207 (TCC)
Royal Courts of Justice
Rolls Building
London, EC4A 1NL
Date: 03/08/2021
Before:
MRS JUSTICE O’FARRELL DBE


Between:
ECO WORLD – BALLYMORE EMBASSY
GARDENS COMPANY LIMITED
Claimant

  • and –
    DOBLER UK LIMITED Defendant


Andrew Rigney QC & Crispin Winser (instructed by DLA Piper UK LLP) for the Claimant
James Bowling (instructed by Fladgate LLP) for the Defendant
Hearing date: 26th January 2021
Further submissions: 18th & 30th March 2021


Approved Judgment
I direct that pursuant to CPR PD 39A para 6.1 no official shorthand note shall be taken of this
Judgment and that copies of this version as handed down may be treated as authentic.
“Covid-19 Protocol: This judgment was handed down by the judge remotely by
circulation to the parties’ representatives by email and release to Bailii. The date
and time for hand-down is deemed to be Tuesday 3rd August 2021 at 10:30am”
………………………..
Mrs Justice O’Farrell DBE
Approved Judgment
E v D
Mrs Justice O’Farrell:

  1. This is the hearing of a Part 8 claim for declarations as to the proper construction and
    effect of the liquidated damages provisions in a construction contract entered into
    between the Claimant (“EWB”) and the Defendant (“Dobler”), in circumstances where
    EWB has taken over part of the works as completed.
  2. EWB’s position is that the liquidated damages clause is void and/or unenforceable. The
    contract permits EWB to take partial possession of the works in advance of practical
    completion but does not contain any mechanism for reducing the level of liquidated
    damages to reflect such early possession. In those circumstances, EWB is entitled to
    claim general damages for delay, including any substantiated damages above the
    contractual liquidated damages cap.
  3. Dobler’s position is that the liquidated damages clause is valid and operable. There is
    an effective mechanism for reducing liquidated damages when partial occupation is
    taken by EWB. Alternatively, if the liquidated damages clause is penal and void,
    general damages are nevertheless capped at the level of liquidated damages in the
    contract.
  4. The parties agree that if the Part 8 Claim fails, judgment should be entered for Dobler
    without the need for enforcement proceedings.
    The Contract
  5. EWB is a property developer. Dobler is the UK subsidiary of the German curtain
    walling and glazing company, Dobler Metallbau GmbH.
  6. By a contract in writing dated 11 July 2016, EWB engaged Dobler as Trade Contractor
    to carry out the design, supply and installation of the façade and glazing works for
    Building A04, part of a development of apartments known as Embassy Gardens Phase
    2, Nine Elms, London SW8 5BA (“the Contract”).
  7. The Contract included the following documents:
    i) Articles of Agreement;
    ii) Trade Contract Particulars;
    iii) The JCT 2011 Construction Management Trade Contract (“the Conditions”),
    subject to a schedule of modifications.
  8. The “Works” were defined in Clause 1.1 of the Conditions as:
    “the work referred to in the Agreement, as more particularly
    shown, described or referred to in the Trade Contract
    Documents, which is to be carried out by the Trade Contractor
    as part of the Project, including any changes made to that work
    in accordance with this Trade Contract.”
  9. The work referred to in the Agreement was:
    Mrs Justice O’Farrell DBE
    Approved Judgment
    E v D
    “the design, supply and installation of facade and glazing works
    (the “Works”) for Building A04 as part of the design and
    construction of Buildings A03, A04 and A05, Embassy Gardens
    Phase 2, Nine Elms, London SW8 5BA (the “Project”).”
  10. Building A04 comprises three residential blocks arranged around a ground level
    courtyard:
    i) Block A is twenty-three storeys in height and provides one hundred and seventy-
    nine high value residential apartments and penthouses;
    ii) Blocks B and C provide eighty affordable housing units over ten-storeys.
  11. The lump sum Contract price was £8,604,809, subject to adjustment in accordance with
    the terms of the Contract.
  12. The Completion Period was defined in clause 1.1 of the Conditions as:
    “the period for completion of the Works or such works in a
    Section as stated in Part 3 of the Trade Contract Particulars (item
    6) or as revised in accordance with these Conditions.”
  13. Part 3 of the Trade Contract Particulars set out the programme for the Works. Following
    design, procurement and materials delivery, the period required for execution of the
    Works on site, after the expiry of the period of notice to commence work, was fifty-
    four weeks.
  14. The Contract did not contain any provision for the Works to be carried out or completed
    within Sections.
  15. Clause 2.5 of the Conditions (as amended) stated:
    “The Works shall be carried out and completed in accordance
    with the programme details stated in Part 3 of the Trade Contract
    Particulars and regularly and diligently and in such order, and at
    such time or times and in such manner as the Construction
    Manager shall instruct, subject, as respects construction but not
    design work, to receipt by the Trade Contractor of notice to
    commence work in accordance with those particulars and subject
    to clauses 2.25 to 2.28. If the Trade Contractor is in breach of the
    foregoing he shall without prejudice to and pending the final
    determination or agreement between the parties as to the amount
    of such loss or damage (if any) suffered or to be suffered by the
    Employer in consequence thereof forthwith pay or allow to the
    Employer such sum as the Employer shall bona fide estimate as
    the amount of such loss or damage such estimate to be binding
    and conclusive upon the Trade Contractor until such final
    determination or agreement.”
    Mrs Justice O’Farrell DBE
    Approved Judgment
    E v D
  16. Clause 2.6 of the Conditions clarified that Dobler, as one of a number of trade
    contractors working on the project, would not have exclusive possession of any part of
    the site when carrying out its Works:
    “The Construction Manager shall permit the Trade Contractor to
    occupy so much of the site of the Project as is reasonably
    required for the execution of the Works, but such occupation
    shall not be exclusive and the Trade Contractor shall not object
    to the use or occupation of that part of the site by any other
    person engaged by the Employer on or in connection with the
    Project unless such use or occupation will or is likely to cause or
    contribute to any delay or obstruction of the Trade Contractor in
    the execution of the Works.”
  17. Clause 2.31 of the Conditions (as amended) stated:
    “.1 The Trade Contractor shall give the Construction
    Manager not less than 10 (ten) Business Days’ notice of
    the date upon which the Trade Contractor considers that
    the Works in any Section will be complete. The
    Construction Manager and representatives of the
    Funder shall be entitled to inspect the Works …
    .2 The Construction Manager shall, within 10 (ten)
    Business Days of any inspection made pursuant to
    clause 2.31.1, notify the Trade Contractor of any
    outstanding matters which require to be attended to
    before the Works in the relevant Section can be
    considered to be complete in accordance with the Trade
    Contract Documents and the Trade Contractor shall
    attend to such matters …
    .3 The Construction Manager shall issue a certificate as to
    the date when practical completion of the Works shall
    be deemed to have taken place for all purposes of the
    Trade Contract …”
  18. Clause 2.32.1 of the Conditions (as amended) contained provisions for liquidated
    damages to be payable in respect of late completion of the Works in the following
    terms:
    “2.32.1 If the Trade Contractor fails to complete the Works or
    works in a Section by the relevant Date for Completion
    of a Section or the Works, the Employer may, not later
    than 5 days before the final date for payment of the
    amount payable under clause 4.16, give notice to the
    Trade Contractor which shall state that for the period
    between the relevant Date for Completion of a Section
    or the Works and the date of practical completion of the
    Works or Section that:
    Mrs Justice O’Farrell DBE
    Approved Judgment
    E v D
    2.32.1.1 he requires the Trade Contractor to pay
    liquidated damages at the rate stated in the
    Trade Contract Particulars, or lesser rate
    stated in the notice, in which event the
    Employer may recover the same as a debt;
    and/or
    2.32.1.2 that he will withhold or deduct liquidated
    damages at the rate stated in the Trade
    Contract Particulars, or at such lesser stated
    rate, from sums due to the Trade Contractor.
    2.32.2 If the Employer intends to withhold or deduct all or any
    of the liquidated damages payable, an appropriate Pay
    Less Notice must be given by or on behalf of the
    Employer. ”
  19. The Trade Contract Particulars specified the rate of liquidated damages applicable
    under the Contract:
    “The following rates of liquidated damages will apply for the
    first 4 weeks (inclusive) of delay in completion of the Works
    beyond the Date for Completion:
  • £nil per week or pro rata for part of a week.
    Liquidated damages will apply thereafter at the rate of £25,000
    per week (or pro rata for part of a week) up to an aggregate
    maximum of 7% of the final Trade Contract Sum…”
  1. Clause 2.33 (as amended) provided for EWB to take over part of the Works prior to
    practical completion of the whole Works:
    “If at any time or times prior to the date of issue by the
    Construction Manager of the certificate of practical completion
    for the Works or such works in a Section that the Employer
    wishes to take over any part or parts of the Works or such works
    in a Section, then, notwithstanding anything expressed or
    implied elsewhere in this Trade Contract, the Employer may take
    over such part or parts. The Construction Manager shall
    thereupon give the Trade Contractor notice identifying the part
    or parts taken over and giving the date when the Employer took
    over those part or parts (“the Relevant Part” and “the Relevant
    Date” respectively).”
  2. Clause 2.34 stated:
    “For the purpose of clauses 2.36 and 4.21.2, practical completion
    of the Relevant Part shall be deemed to have occurred on the
    Relevant Date.”
    Mrs Justice O’Farrell DBE
    Approved Judgment
    E v D
  3. Clause 2.35 provided:
    “As from the Relevant Date the insurance obligations of the
    Employer other than the defects liability protection referred to in
    paragraph 1.2 of Schedule 3 shall terminate in respect of the
    Relevant Part (but not otherwise).”
  4. Clause 2.36 of the Conditions (as amended) provided:
    “.1 If any defects, shrinkages or other faults in the Works
    or such works in a Section appear prior to the Final
    Release Date due to materials, goods or workmanship
    not in accordance with this Trade Contract … or any
    failure of the Trade Contractor to comply with his
    obligations in respect of the Trade Contractor’s Design
    Portion:
    .1 such defects, shrinkages and other faults shall be
    specified by the Construction Manager in a
    schedule of defects which he shall deliver to the
    Trade Contractor as an instruction not later than
    14 days after the Final Release Date; and
    .2 notwithstanding clause 2.36.1.1, the Construction
    Manager may whenever he considers it necessary
    issue instructions requiring any such defect,
    shrinkage or other fault to be made good, provided
    no instructions under this clause 2.36.1.2 shall be
    issued after delivery of a schedule of defects or
    more than 14 days after the Final Release Date.
    .2 Within the period specified in such schedule or
    instructions, the defects, shrinkages and other faults
    shall at no cost to the Employer be made good by the
    Trade Contractor …
    unless the Construction Manager shall otherwise
    instruct …”
  5. The Final Release Date was defined in the Trade Contract Particulars as twenty-four
    months after practical completion of the Works.
  6. Clause 2.37 provided that the Employer should take responsibility for protecting the
    Works or such works in a Section at all times after the date of practical completion.
  7. Clause 4.21.2 and the Trade Contract Particulars provided for retention of three per cent
    to be deducted from the gross valuation of interim certificates in respect of work which
    had not reached practical completion. Half of the retention would be released in respect
    of the valuation of work which had reached practical completion.
    The Works
    Mrs Justice O’Farrell DBE
    Approved Judgment
    E v D
  8. On 8 August 2016 Dobler commenced its work on site.
  9. The original contractual completion date for the Works was 21 August 2017 but, by a
    Deed of Variation with an effective date of 23 January 2018, the parties agreed an
    extended New Completion Date of 30 April 2018:
    “3.1.3 The Parties hereby agree that the 30 April 2018 shall be
    the new completion date for the Works (including the Revised
    Scope) (“New Completion Date”). The term New Completion
    Date shall have the meaning of “Completion Period” where
    stated in the Trade Contract.”
  10. Clause 5 of the Deed of Variation included the following provisions:
    “5.2 Liquidated damages at the rates stated in the Contract
    Particulars may only be levied by the Employer from the New
    Completion Date onwards where applicable pursuant to the
    Trade Contract.
    5.3 Any delay to the Trade Contractor from the Effective Date
    onwards that delays completion of the Works (as revised by the
    Revised Scope) past the New Completion Date are to be dealt
    with in accordance with the provisions of the Trade Contract.”
  11. The Works were not completed by the New Completion Date of 30 April 2018.
  12. During the week ending 15 June 2018, EWB took over Blocks B and C. EWB did not
    issue a practical completion certificate in respect of these parts of the Works.
  13. On 20 December 2018 the Works were certified as having achieved practical
    completion.
    The adjudications
  14. Disputes arose between the parties as to the final account valuation, including
    variations, extensions of time and any liquidated damages payable.
  15. On 7 May 2019 EWB issued a provisional assessment of the Final Trade Contract Sum,
    assessing the final amount as £8,202,631.41. Taking into account the total sum of
    £9,225,761.44 already paid to Dobler, EWB would be entitled to a payment from
    Dobler of £1,023,130. The breakdown attached to the letter showed a deduction of
    £574,184.20 in respect of liquidated damages, stated to be calculated as: “£25,000 a
    week, capped at 7%”.
  16. On 10 May 2019 Dobler issued a pay less notice, assessing the Final Trade Contract
    Sum as £10,646,062.40, which would entitle Dobler to a further payment from EWB
    of £1,420,300.94. The breakdown attached to the letter showed no deduction in respect
    of liquidated damages.
  17. Article 7 of the Articles of Agreement and clause 9.2 of the Conditions provided that
    either party could refer any dispute or difference arising under the Contract to
    adjudication. There have been three adjudications between the parties.
    Mrs Justice O’Farrell DBE
    Approved Judgment
    E v D
  18. The first adjudication between the parties did not result in a decision.
  19. In the second adjudication, Dobler’s position was that EWB took over Blocks B and C
    early, on 15 June 2018; as a result, Blocks B and C were deemed practically complete,
    and thereafter the liquidated damages provision became void and unenforceable for
    uncertainty or because it was operated as a penalty clause. EWB’s position was that it
    had not taken over Blocks B and C and defects in the Works prevented achievement of
    practical completion until 20 December 2018. Further, the liquidated damages of
    £25,000 per week did not amount to a penalty for the continuing delay to Block A alone.
  20. On 15 August 2019 the adjudicator, David White, published his decision, deciding that:
    i) the value of the final Trade Contract Sum was £9,972,627.86,
    ii) EWB was entitled to liquidated damages for delay beyond the New Completion
    Date up to the date on which it took over part of the works;
    iii) on 15 June 2018 EWB took partial occupation Blocks B and C, which amounted
    to deemed practical completion of those blocks and liquidated damages could
    not be levied after that date;
    iv) Dobler was entitled to an extension of time up to 25 June 2018 and, therefore,
    no liquidated damages were payable.
  21. In the third adjudication, Dobler claimed additional sums in respect of its works,
    asserting that liquidated damages were an exhaustive remedy for delay and that EWB
    was not entitled to claim general damages for delay. EWB relied on the decision in the
    second adjudication as rendering the liquidated damages regime void for uncertainty
    or a penalty; as a result, EWB claimed it was entitled to deduct general damages for
    late delivery of Block A in the sum of £2,228,705.85.
  22. On 21 October 2020 the adjudicator, Philip Harris, published his decision, deciding
    that:
    i) he was bound by the decision in adjudication 2 that contractual liquidated
    damages applied up to practical completion of Blocks B and C on 15 June 2018
    but not thereafter;
    ii) the liquidated damages provision was not uncertain or unenforceable as a
    penalty; it was an exhaustive remedy for delay, excluding any entitlement on
    the part of EWB to general damages;
    iii) EWB must pay Dobler £598,135.71 plus VAT, the sum due in respect of
    payment application 30.
    The proceedings
  23. On 28 October 2020 EWB issued these Part 8 proceedings, seeking the Court’s
    determination of the following questions:
    i) Are the liquidated damages provisions in clause 2.32.1 void and/or
    unenforceable?
    Mrs Justice O’Farrell DBE
    Approved Judgment
    E v D
    ii) If so, is EWB entitled to claim general damages for delay and, if so, are any
    recoverable damages limited by reference to the void and/or unenforceable
    provisions of clause 2.32.1?
  24. The remedy sought is declaratory relief in the following terms:
    i) The liquidated damages provisions in clause 2.32.1 are void and/or
    unenforceable.
    ii) The Claimant is therefore entitled to claim general damages for delay.
    iii) The recoverable damages are not limited by reference to the void and/or
    unenforceable provisions of clause 2.32.1.
    iv) The conclusion in the Second Adjudication Decision, to the effect that the
    Claimant was (in principle) entitled to liquidated damages in accordance with
    clause 2.32.1 up to the date on which the Claimant took over part of the Works,
    but not thereafter, is wrong and is not binding on the parties.
    v) The conclusion in the Third Adjudication Decision, to the effect that the
    Claimant was not entitled to claim general damages for delay, is wrong and is
    not binding on the parties. Consequently, the Claimant is entitled to pursue a
    claim for general damages for delay and Mr Harris’s valuation of Application
    30 and his order that the Defendant pay £598,135.71 (plus VAT and interest) to
    the Claimant is not binding on the parties.
    Parties submissions
  25. Mr Rigney QC, leading counsel for EWB, submits that where an employer under a
    construction contract has (and exercises) a contractual right to take early possession,
    but the liquidated damages provisions do not contain a mechanism for reducing the
    level of liquidated damages to reflect such early possession, the liquidated damages
    provisions are void and/or unenforceable. Where liquidated damages provisions are
    void and/or unenforceable, the employer is entitled to recover general damages for
    delay in completion, and the void and/or unenforceable liquidated damages do not cap
    the damages recoverable.
  26. Alternatively, Mr Rigney submits that, irrespective of the position in relation to
    construction contracts in general, clause 2.32.1 of the Trade Contract is void and/or
    unenforceable and EWB is therefore entitled to recover general damages for delay; such
    general damages are not capped at £25,000 per week or an aggregate maximum of 7%
    of the final Trade Contract Sum.
  27. Mr Bowling, counsel for Dobler, submits that under clause 2.34, EWB’s taking over a
    Relevant Part had two limited effects: (i) EWB had to release the first half of the
    retention held for the Relevant Part (clause 4.21.2 and Particulars item 4.21); and (ii)
    Dobler came under a new obligation in respect of the works within a Relevant Part to
    comply with the Construction Manager’s instructions to fix defects as directed (clause
    2.36). However, all other obligations on the part of Dobler continued pending the issue
    of a certificate of practical completion in respect of all works, including its obligation
    to carry out and complete the Works in clause 2.1. Clause 2.32 includes a mechanism
    Mrs Justice O’Farrell DBE
    Approved Judgment
    E v D
    for the rate of liquidated damages to be reduced and therefore avoids rendering the
    provision a penalty in the event that parts of the works are taken over. EWB had
    discretion to deduct the full rate of liquidated damages or a lesser rate, which discretion
    must be exercised reasonably, having regard to its take-over of part of the works.
  28. Mr Bowling submits that if, contrary to Dobler’s primary case, the liquidated damages
    provision is unenforceable, nevertheless it acts as a cap on general damages.
  29. Thus, both parties have performed a volte-face in that they are each arguing the case
    taken by the other side in the adjudications.
    Whether the liquidated damages provision is void and/or unenforceable
  30. The issue is whether, on a true construction, clause 2.32 is penal and/or unenforceable,
    having regard to the provisions for partial take-over of the Works and any mechanism
    for reducing the level of liquidated damages to reflect such take-over.
  31. The leading case on liquidated damages is the decision of the Supreme Court in
    Cavendish Square Holding BV v Makdessi [2015] UKSC 67, in which the penalty test
    was re-stated by Lords Neuberger and Sumption (with whom Lord Carnwath agreed):
    “[31] In our opinion, the law relating to penalties has become the
    prisoner of artificial categorisation, itself the result of
    unsatisfactory distinctions: between a penalty and genuine pre-
    estimate of loss, and between a genuine pre-estimate of loss and
    a deterrent. These distinctions originate in an over-literal reading
    of Lord Dunedin’s four tests and a tendency to treat them as
    almost immutable rules of general application which exhaust the
    field… The real question when a contractual provision is
    challenged as a penalty is whether it is penal, not whether it is a
    pre-estimate of loss. These are not natural opposites or mutually
    exclusive categories. A damages clause may be neither or both.
    The fact that the clause is not a pre-estimate of loss does not
    therefore, at any rate without more, mean that it is penal. To
    describe it as a deterrent (or, to use the Latin equivalent, in
    terrorem) does not add anything. A deterrent provision in a
    contract is simply one species of provision designed to influence
    the conduct of the party potentially affected. It is no different in
    this respect from a contractual inducement. Neither is it
    inherently penal or contrary to the policy of the law. The
    question whether it is enforceable should depend on whether the
    means by which the contracting party’s conduct is to be
    influenced are “unconscionable” or (which will usually amount
    to the same thing) “extravagant” by reference to some norm.
    [32] The true test is whether the impugned provision is a
    secondary obligation which imposes a detriment on the contract-
    breaker out of all proportion to any legitimate interest of the
    innocent party in the enforcement of the primary obligation. The
    innocent party can have no proper interest in simply punishing
    the defaulter. His interest is in performance or in some
    Mrs Justice O’Farrell DBE
    Approved Judgment
    E v D
    appropriate alternative to performance. In the case of a
    straightforward damages clause, that interest will rarely extend
    beyond compensation for the breach, and we therefore expect
    that Lord Dunedin’s four tests would usually be perfectly
    adequate to determine its validity. But compensation is not
    necessarily the only legitimate interest that the innocent party
    may have in the performance of the defaulter’s primary
    obligations.
    [33] The penalty rule is an interference with freedom of contract.
    It undermines the certainty which parties are entitled to expect
    of the law. Diplock LJ was neither the first nor the last to observe
    that “The court should not be astute to descry a ‘penalty clause’”:
    Robophone at p 1447. As Lord Woolf said, speaking for the
    Privy Council in Philips Hong Kong Ltd v Attorney General of
    Hong Kong (1993) 61 BLR 41, 59, “the court has to be careful
    not to set too stringent a standard and bear in mind that what the
    parties have agreed should normally be upheld”, not least
    because “[a]ny other approach will lead to undesirable
    uncertainty especially in commercial contracts.

    [35] … In a negotiated contract between properly advised parties
    of comparable bargaining power, the strong initial presumption
    must be that the parties themselves are the best judges of what is
    legitimate in a provision dealing with the consequences of
    breach.”
  32. Lord Mance, who delivered a concurring judgment, stated at [152]:
    “What is necessary in each case is to consider, first, whether any
    (and if so what) legitimate business interest is served and
    protected by the clause, and, second, whether, assuming such an
    interest to exist, the provision made for the interest is
    nevertheless in the circumstances extravagant, exorbitant or
    unconscionable. In judging what is extravagant, exorbitant or
    unconscionable, I consider (despite contrary expressions of
    view) that the extent to which the parties were negotiating at
    arm’s length on the basis of legal advice and had every
    opportunity to appreciate what they were agreeing must at least
    be a relevant factor.”
  33. Lord Hodge stated the applicable test at [255]:
    “I therefore conclude that the correct test for a penalty is whether
    the sum or remedy stipulated as a consequence of a breach of
    contract is exorbitant or unconscionable when regard is had to
    the innocent party’s interest in the performance of the contract.
    Where the test is to be applied to a clause fixing the level of
    damages to be paid on breach, an extravagant disproportion
    Mrs Justice O’Farrell DBE
    Approved Judgment
    E v D
    between the stipulated sum and the highest level of damages that
    could possibly arise from the breach would amount to a penalty
    and thus be unenforceable. In other circumstances the
    contractual provision that applies on breach is measured against
    the interest of the innocent party which is protected by the
    contract and the court asks whether the remedy is exorbitant or
    unconscionable.”
  34. The commercial benefits to both parties of an effective liquidated damages provision
    was recently considered in Triple Point Technology, Inc v PTT Public Company Ltd
    [2021] UKSC 29 per Lady Arden at [35]:
    “… Parties agree a liquidated damages clause so as to provide a
    remedy that is predictable and certain for a particular event (here,
    as often, that event is a delay in completion). The employer does
    not then have to quantify its loss, which may be difficult and
    time-consuming for it to do…”
    Also, per Lord Leggatt at [74]:
    “A liquidated damages clause is a clause in a contract which
    stipulates what amount of money will be payable as damages for
    loss caused by a breach of the contract irrespective of what loss
    may actually be suffered if a breach of the relevant kind
    (typically, delay in performance of the contract) occurs.
    Liquidated damages clauses are a standard feature of major
    construction and engineering contracts and commonly provide
    for damages to be payable at a specified rate for each week or
    day of delay in the completion of work by the contractor after
    the contractual completion date has passed. Such a clause serves
    two useful purposes. First, establishing what financial loss delay
    has caused the employer would often be an intractable task
    capable of giving rise to costly disputes. Fixing in advance the
    damages payable for such delay avoids such difficulty and cost.
    Second, such a clause limits the contractor’s exposure to liability
    of an otherwise unknown and open-ended kind, while at the same
    time giving the employer certainty about the amount that it will
    be entitled to recover as compensation. Each party is therefore
    better able to manage the risk of delay in the completion of the
    project.”
  35. The starting point for the court is to construe the relevant provisions. It is now well-
    established that, when interpreting a written contract, the court is concerned to ascertain
    the intention of the parties by reference to what a reasonable person, having all the
    background knowledge which would have been available to the parties, would have
    understood them to be using the language in the contract. It does so by focusing on the
    meaning of the relevant words in their documentary, factual and commercial context.
    That meaning has to be assessed in the light of (i) the natural and ordinary meaning of
    the clause, (ii) any other relevant provisions of the contract, (iii) the overall purpose of
    the clause and the contract, (iv) the facts and circumstances known or assumed by the
    parties at the time that the document was executed, and (v) commercial common sense,
    Mrs Justice O’Farrell DBE
    Approved Judgment
    E v D
    but (vi) disregarding subjective evidence of any party’s intentions: Arnold v Britton
    [2015] UKSC 36 per Lord Neuberger Paras.15-23; Rainy Sky SA v Kookmin Bank
    [2011] UKSC 50 per Lord Clarke Paras.21-30; Chartbrook Ltd v Persimmon Homes
    Ltd [2009] UKHL 38 per Lord Hoffmann Paras.14-15, 20-25.
  36. Clause 2.32 of the Conditions provided for liquidated damages to be paid or allowed
    by Dobler if it failed to complete the Works by “the relevant Date for Completion of
    … the Works”.
  37. The Works comprised the façade and glazing works for Blocks A, B and C of Building
    A04 within the development.
  38. Clause 2.5 of the Conditions and Part 3 of the Trade Contract Particulars provided for
    the whole of the Works to be completed within one defined period of fifty-four weeks
    on site. In the Deed of Variation, the parties extended that period and agreed a single
    revised date for completion, namely, 30 April 2018.
  39. The Contract did not contain any provision for sectional completion or specify separate
    completion dates for each block.
  40. Therefore, subject to any extensions of time, Dobler’s liability to pay or allow
    liquidated damages arose if it failed to complete the façade and glazing works for all
    three blocks of Building A04 by 30 April 2018.
  41. Clause 2.32 as drafted contemplated the applicability of liquidated damages in respect
    of any failure to meet (a) contractual dates for completion of sections of the works
    and/or (b) a contractual date for the whole of the works. However, the liquidated
    damages specified in the Trade Contract Particulars were confined to one rate for:
    “delay in completion of the Works beyond the Date for Completion”, subject to the
    grace period of four weeks. The Contract did not provide for an alternative rate of
    liquidated damages that would be applicable to any late completion affecting only one
    of the blocks, or part of the Works.
  42. The natural and ordinary meaning of the words used in the above provisions was that
    Dobler was obliged to complete all its work in Blocks A, B and C, to achieve practical
    completion of the Works. If Dobler failed to complete any of its work in Blocks A, B
    or C by the New Completion Date (or any extended date), EWB would be entitled to
    liquidated damages at the rate set out in Part 3 of the Trade Contract Particulars.
  43. Clause 2.33 entitled EWB to take over part of the Works prior to practical completion.
    However, neither that clause, nor any other provision in the Contract contained any
    mechanism for adjustment to be made to the rate of liquidated damages payable
    thereafter.
  44. Mr Bowling submits that, although clause 2.33 permitted EWB to take over part of
    Dobler’s works prior to practical completion, such take-over was of limited effect under
    the Contract; in particular, deemed practical completion of that part did not relieve
    Dobler of a continuing obligation to complete the works in that part pursuant to clause
    2.1. Clause 2.34 provided that practical completion of any part taken over (“the
    Relevant Part”) would be deemed to have occurred “for the purpose of clauses 2.36
    and 4.21.2”. Mr Bowling correctly points out that clause 2.34 was of limited effect;
    Mrs Justice O’Farrell DBE
    Approved Judgment
    E v D
    Dobler was obliged to rectify defects notified under clause 2.36 in respect of the
    Relevant Part and Dobler became entitled to the release of the first half of retention held
    in respect of the Relevant Part under clause 4.21.2. However, in my judgment, it does
    not follow that taking over part of its work had no further impact on Dobler’s wider
    obligations under the Contract.
  45. The deeming provision contained in clause 2.34 was not expressed to preclude the
    Relevant Part from being treated as practically complete for other purposes.
    Unhelpfully, the term “take over” was not defined in the Contract but in practice the
    effect of such take-over was that the Relevant Part was agreed to be complete. Although
    Dobler did not have any entitlement to exclusive possession of the site, clause 2.6
    obliged EWB to permit Dobler to occupy such part of the site as was reasonably
    required for the execution of the Works. By taking over of part of the Works under
    clause 2.33, EWB effectively excluded Dobler from that part of the site. Once EWB
    took over part of the Works and excluded Dobler from that part, its right to instruct
    further work was limited to defects rectification under clause 2.36. As a result, Dobler
    had no further obligation or right to carry out its work in such part. That was reflected
    in clause 6.3.3 (dealing with liability for damage to the property): “If clause 2.33 has
    been operated, then, after the Relevant Date, the Relevant Part shall not be regarded
    as “’the Works” or “work executed” for the purpose of clause 6.3.1.” Although that
    provision was concerned with property damage, it is indicative of a change in
    contractual status of the Relevant Part that went beyond the deeming provision in clause
    2.34.
  46. Both parties benefitted from early take-over of part of the Works. Dobler’s obligation
    to carry out that part of the Works ceased and was replaced by its obligation to rectify
    defects under clause 2.36. Dobler became entitled to release of half of the retention in
    respect of the value of the Relevant Part under clause 4.21.2. EWB also benefitted from
    early completion of part of the Works. Separate obligations were owed by EWB to the
    relevant local authority to complete Blocks B and C by specified dates, failing which
    liquidated damages would become payable by EWB. Taking over Blocks B and C prior
    to completion of the Works enabled EWB to progress the follow-on trades in those
    blocks and hand them over to the local authority, thus avoiding or reducing any liability
    for liquidated damages. Taking over Block A prior to practical completion enabled
    EWB to lease or sell the apartments, generating early revenues or reducing financing
    costs.
  47. In summary, as a matter of construction, the Contract entitled EWB to take over part of
    the Works prior to practical completion. Both parties benefitted from operation of
    clause 2.33. However, Dobler was not entitled to any relief from liquidated damages to
    reflect such take-over. The full rate of liquidated damages continued to be applicable
    to the reduced scope of the outstanding works.
  48. Mr Rigney submits that where an employer under a construction contract has (and
    exercises) a contractual right to take early possession, but the liquidated damages
    provisions do not contain a mechanism for reducing the level of liquidated damages to
    reflect such early possession, the liquidated damages provisions are void and/or
    unenforceable. Reliance for that proposition is placed on the following extracts from
    the leading construction law textbooks:
    Keating on Construction Contracts (11th Edition) (2021) at paragraph 10-023:
    Mrs Justice O’Farrell DBE
    Approved Judgment
    E v D
    “Difficulties can arise where a single sum is stipulated for
    liquidated damages but the works are to be completed in sections
    at different times or where the employer takes possession of part
    of the works before completion of the whole. Unless there are
    effective provisions for dividing the single sum between the
    sections or reducing it in proportion to the part taken into
    possession, a claim for liquidated damages will fail.”
    Hudson’s Building and Engineering Contracts (14th Edition) (2020) at paragraph 6-024:
    “… in the absence of a properly completed contractual
    mechanism for sectional completion and accompanying
    liquidated damages, it has been held the liquidated damages
    clauses are liable to be rendered inoperable or invalidated
    through the Employer taking possession of a section of the
    works. Unless there are effective provisions for dividing the
    single sum between the sections or reducing it in proportion to
    the part taken into possession, a claim for liquidated damages
    will fail.”
  49. It is important not to elevate statements of general principle into an inflexible rule of
    law. The above extracts do not state that liquidated damages provisions will never be
    enforceable where sectional completion or partial possession is used without any related
    reduction in the liquidated damages payable; they identify the potential danger of
    failing to draft effective provisions to respond in such circumstances. In each case, it is
    necessary to construe the relevant provisions of the contract in question, adopting the
    established rules of contractual interpretation, to determine whether they give rise to a
    liquidated damages regime that is certain and enforceable.
  50. When construing the relevant provisions of the Contract to determine whether the
    liquidated damages regime is operable, it is helpful to consider the cases cited by Mr
    Rigney in support of his argument.
  51. In Bramall & Ogden v Sheffield City Council (1983) 29 BLR 73 His Honour Judge
    Hawser QC held that a liquidated damages provision was unenforceable and a penalty
    because the mechanism for calculating such damages where partial possession was
    taken did not work. The contract in that case provided for the contractor to construct
    123 dwellings and associated works. Clause 22 provided for payment of “a sum
    calculated at the rate stated in the Appendix as Liquidated and Ascertained Damages”
    in respect of any failure to complete the works by the contractual date for completion.
    The rate for liquidated damages in the Appendix was expressed as “at the rate of £20
    per week for each uncompleted dwelling”. There was no contractual provision for
    sectional completion but as individual houses were completed they were taken over by
    the employer by consent. Clause 16(e) of the contract provided:
    “In lieu of any sum to be paid or allowed by the Contractor under
    clause 22 of these Conditions in respect of any period during
    which the works may remain incomplete occurring after the date
    on which the Employer shall have taken possession of the
    relevant part there shall be paid or allowed such sum as bears the
    same ratio to the sum which would be paid or allowed apart from
    Mrs Justice O’Farrell DBE
    Approved Judgment
    E v D
    the provisions of this Condition as does the Contract Sum less
    the total value of the relevant part to the Contract Sum.”
    The intention was that where parts of the works were taken into possession by consent,
    the sum to be paid or allowed as liquidated damages should be proportionately reduced
    on the basis of the value of the occupied part relative to the full contract sum. The court
    found that the provision was inoperable by reason of the inconsistency between clause
    16(e) and the Appendix; the calculation required in clause 16(e) could not be carried
    out by reference to a rate per uncompleted dwelling, rather than a specific rate for the
    whole of the works, particularly in circumstances where the works were not confined
    to the construction of the dwellings.
  52. His Honour Judge Hawser QC stated at p.85-89:
    “Mr Stimpson’s argument may I hope be summarised as follows.
    The “Works” cover not only the houses but the other items above
    referred to. Condition 22 refers to a failure “to complete the
    Works” by the extended date. As from that date the employer
    becomes entitled to liquidated damages until the Works are
    completed. Clause 16 deals with the consensual taking of
    possession of part of the Works. Condition 16(e) provides for the
    sum payable after taking possession in respect of the period
    during which the Works remain incomplete. The way in which
    the liquidated damages are dealt with is set out in the Appendix.
    This does not allow of the calculation to be made which is
    required by Condition 16(e), and one cannot operate the
    Appendix and Condition 16(e) in the circumstances of this case.
    The inconsistency can only be reconciled if provision is made in
    the contract for sectional completion of those parts which are
    taken over and to which specific liquidated damages provisions
    are applied …
    There is no doubt that the applicants’ argument is a very
    technical one, but I think that it is correct …
    I think one must read and give effect to both conditions. I do not
    think one can avoid the conclusion that Condition 16(e) would
    apply to the present situation, and it does not seem to be
    consistent with the liquidated damages as set out in the
    Appendix.
    It would of course be open to the parties to have made
    appropriate provision in the contract itself so as to deal with the
    situation …
    It seems to me, therefore, that in the absence of any provision for
    sectional completion in this contract, the respondents were not
    entitled to claim or deduct liquidated damages as provided in the
    Appendix.”
    Mrs Justice O’Farrell DBE
    Approved Judgment
    E v D
  53. The decision in Bramall & Ogden was referred to by Her Honour Judge Kirkham in
    Avoncroft Construction Limited v Sharba Homes (CN) Limited [2008] EWHC 933
    (TCC) at [3] to [7]. However, that case concerned the enforcement of an adjudicator’s
    decision. The central issue was whether any entitlement to liquidated damages could be
    set-off against the sum awarded by the adjudicator. Having decided that no set-off was
    available, it was unnecessary for the judge to analyse the contract provisions to
    determine the issue of entitlement to liquidated damages.
  54. Another example of inoperability arose in the case of Taylor Woodrow Holdings
    Limited v Barnes & Elliott Limited [2004] EWHC 3319 (TCC). In that case, although
    the contract provided for sectional completion and a pro-rata adjustment of liquidated
    damages to take account of partial possession, the adjustment could not be calculated
    because the scope of works falling within each section was not adequately defined or
    capable of ascertainment from the contract documents. On that basis, His Honour Judge
    Wilcox held that the liquidated damages provision was void for uncertainty at [22]:
    “It follows inexorably that if for the purposes of clause 24 the
    contents of any section were not ascertained in the contract, or
    any mechanism agreed between the parties whereby they could
    be ascertained, there is no basis for triggering the operation of
    clause 24 since it would be uncertain what had remained undone
    and when. The arbitrator so found. In my judgment his
    construction of the contract was correct. Clause 24 was void for
    uncertainty; it was incapable of operation. Clause 17.1.4 was
    inoperable. By virtue of that, where partial possession was given,
    the proportionate relief from any LADs on the section was
    incapable of calculation. Any LADs, referred as they were to
    living units, however comprised, would not bear a proper
    relationship to the extent of the section not take into possession.”
  55. Thus, in the cases above, the courts did not reject, as automatically fatal, the concept of
    one rate of liquidated damages for late completion of the works where there is sectional
    completion or partial possession; rather, the express provisions in each case simply did
    not work because of errors in drafting.
  56. As a matter of construction, the provisions in this case are reasonably clear and certain.
    There is one completion date for the whole of the Works. Liquidated damages are
    payable at the rate set out in the Trade Contract Particulars for failure to complete the
    whole of the Works by the completion date. There is no reduction in the rate of
    liquidated damages where partial completion is achieved or the employer takes over
    part of the Works prior to practical completion. Such provisions are capable of being
    operated. The Contract in this case does not give rise to the difficulties found in
    Brammell v Ogden or Barnes & Elliott that rendered the provisions void and
    unenforceable.
  57. The issue that then arises is whether the liquidated damages provision, as construed
    above, is penal and unenforceable as submitted by Mr Rigney on behalf of EWB. The
    basis of that submission is the use of the same rate of liquidated damages as
    compensation for late completion of any combination of Blocks A, B and/or C, despite
    the fact that different levels of loss would be incurred; in particular, where EWB chose
    to exercise its right under clause 2.33 to take over part of the works.
    Mrs Justice O’Farrell DBE
    Approved Judgment
    E v D
  58. That issue is certainly a factor that the court must consider. In Dunlop Pneumatic Tyre
    Co Ltd v New Garage and Motor Co [1915] AC 79, one of Lord Dunedin’s tests was
    that there was a presumption (but no more) that a provision would be penal: “when a
    single lump sum is made payable by way of compensation, on the occurrence of one or
    more or all of several events, some of which may occasion serious and others but trifling
    damage”. In some cases the use of a single rate of liquidated damages payable
    regardless whether 10% or 90% of a development is handed over, or completed, after
    the contractual date for completion, might indicate that the liquidated damages
    provision amounted to a penalty; but in other cases, it might not. Mr Rigney accepted
    that, as a matter of principle, a rate of liquidated damages that was objectively modest
    would not amount to a penalty simply because it applied to a number of different
    breaches. Each provision must be considered in the context of the contract as a whole.
  59. In my judgment, applying the test set out in Cavendish Square, the liquidated damages
    provision in this case is not unconscionable or extravagant so as to amount to a penalty
    for the following reasons.
  60. Firstly, the liquidated damages provision was negotiated by the parties, who both had
    the benefit of advice from external lawyers, as explained by Daniel Rauh, the Managing
    Director of Dobler, in his witness statement. The court should be cautious about any
    interference in the freedom of the parties to agree commercial terms and allocation of
    risk in their business dealings. As noted by Lord Leggatt in Triple Point (above), such
    a provision limits the contractor’s exposure to an unknown and open-ended liability,
    while at the same time giving the employer certainty about the amount that it will be
    entitled to recover as compensation. Each party is therefore better able to manage the
    risk of delay in the completion of the project.
  61. Secondly, EWB had a legitimate interest in enforcing the primary obligation of Dobler
    to complete the Works as a whole by the New Completion Date. Late completion of
    any part of the Works was likely to have an adverse impact on the work of following
    trade contractors carrying out fit out and other finishing works, causing not just delay
    but also disruption to the project as a whole. Late completion of Blocks B and/or C
    would expose EWB to liability for liquidated damages to the local authority. Late
    completion of Block A would expose EWB to the risk of losing purchasers for the
    apartments.
  62. Thirdly, quantification of the damages that would be suffered by EWB would be
    difficult, particularly if part, but not all, of the Works were completed on time. Different
    combinations of partially incomplete blocks could result in a wide range of the
    categories of loss referred to above. By fixing in advance the liquidated damages
    payable for late completion of the whole Works, the parties avoided the difficulty of
    calculating and proving such loss.
  63. Fourthly, the level of damages was set at £25,000 per week (or pro rata for part of a
    week), with a grace period of four weeks and a maximum of 7% of the Trade Contract
    Sum, a cap of £602,336.63 at the date of the Contract. There is no evidence before the
    court, and it has not been suggested by either party, that such level of damages was
    unreasonable or disproportionate to the likely losses in the event of late completion of
    the work in any one or more of the blocks forming part of Building A04.
    Mrs Justice O’Farrell DBE
    Approved Judgment
    E v D
  64. In those circumstances, the liquidated damages provision is not extravagant, exorbitant
    or unconscionable. It is a secondary obligation which imposes a detriment on Dobler
    which is proportionate to the legitimate interest of EWB in the enforcement of the
    primary obligation of completion of the Works in accordance with the terms of the
    Contract. In conclusion, the liquidated damages provision is valid and enforceable.
    Alternative argument as to clause 2.32
  65. Although not necessary given the above conclusion, for completeness I have considered
    Dobler’s alternative argument that clause 2.32 contains a mechanism for reducing
    liquidated damages that would save the provision if otherwise inoperable.
  66. Clause 2.32 provides that EWB may give notice that it requires Dobler to pay:
    “liquidated damages at the rate stated in the Trade Contract
    Particulars, or lesser rate stated in the notice.”
  67. Mr Bowling submits that where a party reserves to itself discretion to set a rate or price,
    a term is implied that such discretion must not be exercised unreasonably. Where there
    has been partial take-over of work, it would be unreasonable to deduct full liquidated
    damages. An unreasonable exercise of discretion would fall outside the scope of clause
    2.32 and be invalid. If EWB takes over part of the Works but wishes to preserve its
    entitlement to liquidated damages, it must serve notice setting a new, lesser rate, within
    the reasonable range of values having regard to the nature scope and extent of any
    Relevant Part taken over that would reduce EWB’s delay-based losses.
  68. The leading case on the implication of terms of rationality or reasonableness as a
    constraint on the exercise of contractual discretion is Braganza v BP Shipping [2015]
    UKSC 17, in which Lady Hale (with whom Lord Kerr agreed) stated:
    “[18] Contractual terms in which one party to the contract is
    given the power to exercise a discretion, or to form an opinion
    as to relevant facts, are extremely common. It is not for the courts
    to re-write the parties’ bargain for them, still less to substitute
    themselves for the contractually agreed decision-maker.
    Nevertheless, the party who is charged with making decisions
    which affect the rights of both parties to the contract has a clear
    conflict of interest. That conflict is heightened where there is a
    significant imbalance of power between the contracting parties
    as there often will be in an employment contract. The courts have
    therefore sought to ensure that such contractual powers are not
    abused. They have done so by implying a term as to the manner
    in which such powers may be exercised, a term which may vary
    according to the terms of the contract and the context in which
    the decision-making power is given.
    [21] … In Paragon Finance plc v Nash [2001] EWCA Civ 1466,
    [2002] 1 WLR 685, the court had to consider whether there was
    any implied term limiting the power of a mortgagee to set interest
    rates under a variable rate mortgage. Dyson LJ had no difficulty
    in holding (at paras 32 to 36) that it was necessary, in order to
    Mrs Justice O’Farrell DBE
    Approved Judgment
    E v D
    give effect to the reasonable expectations of the parties, to imply
    a term that the power would not be exercised dishonestly, for an
    improper purpose, capriciously or arbitrarily. He went on to
    discuss whether there should also be a term that the power would
    not be exercised unreasonably. He concluded that there had been
    a “somewhat reluctant” extension of the implied term to include
    “unreasonableness that is analogous
    to Wednesbury unreasonableness” (paras 37 to 42).”
    [22] These authorities, together with Ludgate Insurance Co Ltd
    v Citibank NA [1998] Lloyd’s Rep IR 221, 239-240, and Gan
    Insurance Co Ltd v Tai Ping Insurance Co Ltd (No 2) [2001]
    EWCA Civ 1047, [2001] 2 All ER (Comm) 299, at paras 64, 67,
    73, are helpfully summarised by Rix LJ in Socimer International
    Bank Ltd v Standard Bank London Ltd [2008] EWCA Civ
    116, [2008] Bus LR 1304. In his conclusion, at para 66, he
    substitutes the more modern term “irrationality” for
    unreasonableness:
    “It is plain from these authorities that a decision-maker’s
    discretion will be limited, as a matter of necessary
    implication, by concepts of honesty, good faith, and
    genuineness, and the need for the absence of
    arbitrariness, capriciousness, perversity and
    irrationality. The concern is that the discretion should
    not be abused. Reasonableness and unreasonableness
    are also concepts deployed in this context, but only in a
    sense analogous to Wednesbury unreasonableness, not
    in the sense in which that expression is used when
    speaking of the duty to take reasonable care, or when
    otherwise deploying entirely objective criteria: as for
    instance when there might be an implication of a term
    requiring the fixing of a reasonable price, or a
    reasonable time. In the latter class of case, the concept
    of reasonableness is intended to be entirely mutual and
    thus guided by objective criteria. … Laws LJ in the
    course of argument put the matter accurately, if I may
    respectfully agree, when he said that pursuant to
    the Wednesbury rationality test, the decision remains
    that of the decision-maker, whereas on entirely
    objective criteria of reasonableness the decision-maker
    becomes the court itself.””
  69. A distinction can be drawn between the exercise of discretion by one party under a
    contract, where such a term may be implied, and the exercise of an absolute contractual
    right by a party, where such a term is unnecessary. In Mid-Essex Hospital Services NHS
    Trust v Compass Group UK and Ireland Ltd [2013] EWCA Civ 200 Jackson LJ
    considered the earlier authorities then available in respect of a contractual provision
    entitling the trust to award service failure points at [83]:
    Mrs Justice O’Farrell DBE
    Approved Judgment
    E v D
    “An important feature of the above line of authorities is that in
    each case the discretion did not involve a simple decision
    whether or not to exercise an absolute contractual right. The
    discretion involved making an assessment or choosing from a
    range of options, taking into account the interests of both parties.
    In any contract under which one party is committed to exercise
    such a discretion, there is an implied term. The precise
    formulation of that term has been variously expressed in the
    authorities. In essence, however, it is that the relevant party will
    not exercise its discretion in an arbitrary, capricious or irrational
    manner. Such a term is extremely difficult to exclude, although
    I would not say it is utterly impossible to do so.”
  70. Having considered the contractual framework for the calculation of service failure
    points and the Trust’s discretion to impose them, Jackson LJ determined that an implied
    term did not arise in that case:
    “[91] The discretion which is entrusted to the Trust in relation to
    service failure points and deductions in the present case is very
    different from the discretion which existed in the authorities
    discussed above. The Trust is a public authority delivering a vital
    service to vulnerable members of the public. It rightly demands
    high standards from all those with whom it contracts. There may,
    of course, be circumstances in which the Trust decides to award
    less than the full amount of service failure points or to deduct
    less than it is entitled to deduct from a monthly payment.
    Nevertheless the Trust could not be criticised if it awards the full
    number of service failure points or if it makes the full amount of
    any deduction which it is entitled to make. The discretion
    conferred by clause 5.8 simply permits the Trust to decide
    whether or not to exercise an absolute contractual right.
    [92] There is no justification for implying into clause 5.8 a term
    that the Trust will not act in an arbitrary, irrational or capricious
    manner. If the Trust awards more than the correct number of
    service failure points or deducts more than the correct amount
    from any monthly payment, then there is a breach of the express
    provisions of clause 5.8. There is no need for any implied term
    to regulate the operation of clause 5.8.”
  71. In Equitas Insurance Limited v Municipal Mutual Insurance Limited [2019] EWCA
    Civ 718 Males LJ emphasised the necessity for the relevant provision to be construed
    as part of the contract before determining whether the provision was one to which any
    implied term would apply:
    “[113] … Although the Mid Essex case uses the expression
    “absolute contractual right” that is the result of a process of
    construction which takes account of the characteristics of the
    parties, the terms of the contract as a whole and the contractual
    context, not a starting point intrinsic to the term itself. It is only
    possible to say whether a term conferring a contractual choice on
    Mrs Justice O’Farrell DBE
    Approved Judgment
    E v D
    one party represents an absolute contractual right after that
    process of construction has been undertaken.”
  72. In TAQA Bratani Ltd v RockRose [2020] 2 Lloyd’s Rep 64 His Honour Judge Pelling
    QC (sitting as a High Court Judge) cautioned against unnecessary interference with the
    contractual freedom of the parties in commercial contracts:
    “[53] Absolute rights conferred by professionally drawn or
    standard form contracts including but not limited to absolute
    rights to terminate relationships and roles within relationships
    are an everyday feature of the contracts that govern commercial
    relationships and extending Braganza to such provisions would
    be an unwarranted interference in the freedom of parties to
    contract on the terms they choose, at any rate where there is no
    fiduciary relationship created by the agreement …”
  73. In his further written submissions, Mr Bowling accepts, in my view correctly, that there
    may be no room for an implied term requiring a discretion to be operated rationally if
    the process of construction indicates that the clause confers absolute contractual rights
    intended to be exercised in a party’s own judgment.
  74. In my judgment, there is no room for an implied term in this case. Firstly, as a matter
    of construction, clause 2.32 expressly gives EWB a contractual right to deduct
    liquidated damages at the rate set out in the Trade Contract Particulars. That amounts
    to an absolute contractual right. The court would be reluctant to go behind the allocation
    of risk negotiated by the parties, with the benefit of legal advice, when agreeing the
    commercial terms of the Contract. There is no need to imply any term that such
    contractual right must be exercised in a rational or reasonable manner in order to make
    that provision work.
  75. Secondly, even if the court considered that it was necessary to imply a term that EWB
    would not act in an arbitrary, capricious or irrational manner when levying liquidated
    damages, consistent with the explanation set out by Lady Hale in Braganza, that would
    be limited to the circumstances in which EWB could operate the provision, namely,
    whether there was any logical connection between late completion of any part of the
    Works and the ostensible reasons given by EWB for the decision to deduct liquidated
    damages. It would not extend to an implied term of reasonableness as to any objective
    assessment of the appropriate amount of liquidated damages to be levied.
  76. Thirdly, even if a term of reasonableness were to be implied, the Contract contains no
    mechanism for determining any reasonable level of reduced damages, or the factors that
    should be taken into account when fixing such “lesser amount”. As Mr Rigney
    succinctly observed, in such circumstances, the clause would no longer be a liquidated
    damages provision.
  77. For the above reasons, Dobler’s alternative argument based on an implied term would
    not save the liquidated damages provision, if otherwise unenforceable for uncertainty
    or as a penalty.
    If clause 2.32 is penal and/or unenforceable, whether any general damages are nevertheless
    “capped” at the level of liquidated damages otherwise payable
    Mrs Justice O’Farrell DBE
    Approved Judgment
    E v D
  78. It is not strictly necessary for the court to decide this issue, having found that the
    liquidated damages provision was valid and enforceable. However, as it has been
    argued in full, the court has considered it briefly.
  79. It is common ground that where a liquidated damages provision has been held to be
    unenforceable as uncertain or a penalty, the employer is entitled to prove actual loss
    and claim unliquidated damages: Rapid Building Group Ltd v Ealing Family Housing
    Association Ltd (1984) 29 BLR 5 per Stephenson LJ at p.16.
  80. EWB’s case is that, in such circumstances, the unenforceable liquidated damages
    provision does not operate as a cap on the recoverable general damages. The innocent
    party can sue for general damages and the unenforceable liquidated damages clause is
    simply ignored.
  81. Dobler’s case is that the unenforceable liquidated damages provision acts as a cap on
    general damages.
  82. Both parties helpfully drew the court’s attention to the positions adopted by the
    textbooks as follows:
    Keating (11th edition) at paragraph 10-029:
    “There is authority in charterparty cases suggesting that a
    claimant can recover more than the agreed sum if it is held to be
    a penalty. On the other hand there are judicial indications to the
    contrary. It is suggested that the charterparty cases are special to
    the clauses in question, and that in construction contracts the
    question is open. It is submitted that it would be inequitable to
    permit an employer to avoid the effect of a provision which was
    penal in order to recover more. Further, where the nature of the
    clause is usually to limit the contractor’s liability (as suggested
    above), there is every reason why the contractor should not be
    denied that limitation simply because the employer’s estimate of
    its loss was not genuine.”
    Hudson (14th edition) at paragraph 6-050:
    “Unless there is some independent reason why the Contractor
    should not have the benefit of an agreed limiting sum, restricting
    the Employer’s general damages to the liquidated amount
    without further enquiry will secure any such benefit for the
    Contractor, if it exists, while removing the need to investigate
    the precise makeup of the liquidated sums. Nevertheless, while
    treating liquidated damages as a “cap” on general damages
    appears to have been recognised since the early cases, the point
    may be open and a more precise statement of its rationale in
    construction cases is still awaited.”
    Chitty on Contracts (33rd edition with supplement)(2020) at paragraph 26-243:
    Mrs Justice O’Farrell DBE
    Approved Judgment
    E v D
    “A clause which is not a genuine pre-estimate, e.g. because it
    stipulates for more than the likely loss, and which is therefore a
    penalty, may be ignored if it is for less than the actual damage
    suffered. Where a charterparty contained the following clause:
    “[p]enalty for non-performance of this agreement proved
    damages, not exceeding estimated amount of freight”, it was
    held that the clause provided a penalty and not a limitation of
    liability, so that the party complaining of non-performance was
    entitled to recover damages for his actual loss although it
    exceeded the estimated amount of freight. It is unsettled whether
    this principle applies to penalty clauses in other types of contract,
    so as to entitle the claimant to ignore the sum stipulated as a
    penalty (where it was clearly not intended to limit liability) and
    to sue for damages for a greater amount to compensate him for
    his actual loss.”
    McGregor on Damages (21st edition) (2021) at paragraph 16-029:
    “Just as the penalty cannot augment his damages so too the
    claimant will not be restricted to the penalty in the rare cases
    where it is less than the actual damage… It was early held in
    Winter v Trimmer, and again in Harrison v Wright, that the
    claimant could ignore this penal stipulation and recover for his
    greater loss. The same result was reached in the last century in
    Wall v Rederiaktiebolaget Luggude where Bailhache J retraced
    the law in a very useful judgment which remains the clearest
    authority for the present rule. However the wording of the clause
    had become more complex and the earlier cases provide more
    useful illustrations of circumstances in which a penalty is likely
    to turn out less than the actual damage. The decision itself was
    approved soon after as to its interpretation of the particular
    clause as a penalty by the House of Lords in Watts v Mitsui, and,
    as Scrutton LJ pointed out in Widnes Foundry v Cellulose
    Acetate Silk Co, Lord Sumner clearly took the view that “the
    clause did not prevent the shipowners or charterers from
    recovering the actual amount of damage, though it might be more
    than the estimated amount of freight”. In view of this line of
    authority, the occasional dicta which state that the penalty marks
    the ceiling of recovery are unacceptable. They are probably
    based upon the historical fact that the sum in a penal bond fixed
    the maximum amount recoverable.”
  83. Therefore, all the textbooks recognise the line of authority in charterparty cases that
    permits an innocent party to ignore the penalty clause and recover its actual loss,
    whether more or less than the sum stipulated in the penalty clause. The editors of
    Keating, Hudson and Chitty consider that the position is unsettled in other types of
    contract. In Keating and Hudson it is noted that there is merit in treating the liquidated
    damages cap as an agreed limitation on damages for the benefit of the contractor. The
    editors of McGregor consider that the charterparty line of authority is clear and dicta
    suggesting the penalty acts as a cap are wrong.
    Mrs Justice O’Farrell DBE
    Approved Judgment
    E v D
  84. In Wall v Rederiaktiebolaget Luggude [1915] 3 KB 66, Bailhache J summarised the
    position in relation to penalties in charterparties at p.73:
    “You cannot under it recover more than the proved damages, and
    if proved damages exceed the penal sum you are restricted to the
    lower amount. As a penalty clause may be disregarded it is
    always disregarded and has become a dead letter, or from another
    point of view, a “brutum fulmen”, as Blackburn J called it in
    Godard v Gray LR 6 QB at p 148.”
  85. In Watts, Watts & Co v Mitsui [1917] AC 227, another charterparty case, the House of
    Lords approved Bailhache J’s analysis in Wall. Lord Finlay LC stated in respect of the
    penalty clause at p.235:
    “If this clause had appeared for the first time I think it might have
    been construed as imposing a limitation on the damages to be
    recovered, but the penalty clause is an old one with a settled
    meaning, and the intention, if it existed, to make so fundamental
    a change in its effect as is suggested ought to have been much
    more clearly shown in order to bind the other party to the
    contract.
    In my opinion the judgments of Bailhache J. in the present and
    in the earlier case before him on this point were right.”
  86. Lord Dunedin agreed (at p.245) and Lord Sumner stated at p.246:
    “I have no doubt that clause 13 is a penalty clause and immaterial
    in the present case. … The whole matter has been fully and, if I
    may say so, admirably discussed by Bailhache J. in the recent
    case of Wall v. Rederiaktiebolaget Luggude. Your Lordships
    decided the point in Ströms Bruks Aktie Bolag v. Hutchison
    upon a somewhat similar clause, and I think that the present case
    cannot really be distinguished. My only difficulty is to
    understand why such a provision should be inserted at all.”
  87. The point was expressly left open in Cellulose Acetate Silk Co Ltd v Widnes Foundry
    (1925) Ltd [1933] AC 20, per Lord Atkin at p.26:
    “I desire to leave open the question whether, where a penalty is
    plainly less in amount than the prospective damages, there is any
    legal objection to suing on it, or in a suitable case ignoring it and
    suing for damages.”
  88. In Robophone Facilities Limited v Blank [1966] 1 WLR 1428, Diplock LJ raised the
    question as undecided but declined to answer it at p.1446E-H:
    “Where the court refuses to enforce a “penalty clause” of this
    nature, the injured party is relegated to his right to claim that
    lesser measure of damages to which he would have been entitled
    Mrs Justice O’Farrell DBE
    Approved Judgment
    E v D
    at common law for the breach actually committed if there had
    been no penalty clause in the contract.
    I make no attempt, where so many others have failed, to
    rationalise this common law rule. It seems to be sui generis. The
    court has no general jurisdiction to re-form terms of a contract
    because it thinks them unduly onerous on one of the parties –
    otherwise we should not be so hard put to find tortuous
    constructions for exemption clauses, which are penalty clauses
    in reverse: we could simply refuse to enforce them. Again, it is
    by no means clear that “penalty clauses” are simply void, like
    covenants in unreasonable restraint of trade. There are dicta
    either way, and in Cellulose Acetate Silk v. Widnes Foundry Lord
    Atkins expressedly left open the question whether a penalty
    clause in a contract, which fixed a single sum as payable upon
    breach of a number of different terms of the contract, some of
    which breaches may occasion only trifling damage but others
    damage greater than the stipulated sum, would be treated as
    imposing a limit on the damages recoverable in an action for a
    breach in respect of which it operated to reduce the damages
    which would otherwise be recoverable at common law.”
  89. In Cavendish Square (above) Lords Neuberger and Sumption (with whom Lord
    Carnwarth agreed) stated that the consequence of a damages provision being held to be
    a penalty was that the clause would be wholly unenforceable. They specifically rejected
    the suggestion by the Court of Appeal in Jobson v Johnson [1989] 1 WLR 1026 that a
    penalty provision could be partially enforced on a scaled down basis, i.e. only to the
    extent of any actual loss suffered by the breach:
    “[9] the penalty clause is wholly unenforceable … Deprived of
    the benefit of the provision, the innocent party is left to his
    remedy in damages under the general law.

    [87] If, as the authorities show, the penal consequences of a
    contractual provision fall to be determined as at the time of the
    agreement, and a provision found to be a penalty is
    unenforceable, it is impossible to see how it can be enforceable
    on terms.”
  90. Lord Hodge agreed with that stated position on partial enforceability at [283]:
    “In English law a penalty clause cannot be enforced. For the
    reasons given by Lord Neuberger and Lord Sumption in their
    judgment (at paras 84-87) I think that the decision of the Court
    of Appeal in Jobson v Johnston was incorrect in so far as it
    modified a penalty clause and should be overruled.”
  91. This issue was considered in the context of an option to acquire shares, rather than a
    liquidated damages provision and the Supreme Court did not expressly consider
    Mrs Justice O’Farrell DBE
    Approved Judgment
    E v D
    whether a penalty clause could operate as a cap on general damages. However, as Mr
    Rigney submits, if a penalty were held to operate as a cap, it would not be wholly
    unenforceable. Therefore, Cavendish Square provides persuasive support for the view
    that if a liquidated damages provision is void for uncertainty or as a penalty, it is wholly
    unenforceable and the employer’s entitlement to general damages will not be subject to
    a cap.
  92. However, it does not follow that such provision will have no contractual effect; even
    where a liquidated damages clause is found to be wholly unenforceable as a penalty, it
    may on a true construction be found to operate as a limitation of liability provision.
  93. In this case a further issue that arises is whether clause 2.32.1 together with the Trade
    Contract Particulars simply amounted to an agreed liquidated damages provision or
    whether it should be construed also as a limitation of liability provision.
  94. The relevant words used were:
    “Liquidated damages will apply … at the rate of £25,000 per
    week (or pro rata for part of a week) up to an aggregate
    maximum of 7% of the final Trade Contract Sum…”
  95. Mr Bowling submits that the clear intention of the parties was that Dobler would not
    pay more than £25,000 per week if it fell into culpable delay. The fact that the
    mechanism for imposing that liability might fail ought not to detract from their bargain
    in this regard. Further, the agreement that delay damages would be capped at 7% of the
    Trade Contract Sum was an independent covenant on the part of EWB that operates as
    a limitation of liability provision in any event.
  96. Mr Rigney submits that liquidated damages clauses are, by definition, not exclusion
    clauses or limitation of liability clauses, relying on: Suisse Atlantique Societe
    d’Armement SA v NV Rotterdamsche Kolen Centrale [1967] 1 AC 361 per Lord Upjohn
    at 421D; K Line PTE Ltd v Priminds Shipping (HK) Co Ltd [2020] EWHC 2373
    (Comm) per Andrew Baker J at [55(ii)] and [59(iii)]. He acknowledges that a clause
    might be drafted in such a way that the parties should be taken to have intended it to
    operate as both as a liquidated damages clause and also as a limitation of liability clause,
    but such an intention would have to be clear from the words used. He submits that there
    is nothing in the wording of clause 2.32.1 that leads to the conclusion that this is what
    the parties intended.
  97. Each clause must be construed in accordance with the established principles of
    contractual interpretation summarised above. In my judgment, clause 2.32.1 and the
    Trade Contract Particulars would operate as a limitation of liability provision, even if
    the liquidated damages were void or a penalty. Having regard to their Lordships’
    opinions in Cavendish Square, the agreed damages of £25,000 per week would fall
    away as unenforceable but the court would strive to give effect to the separate part of
    the provision containing an express limitation on liability at 7% of the final Trade
    Contract Sum. A literal reading of the provision suggests that the 7% cap would apply
    only to the liquidated damages and not to any general damages. However, the objective
    understanding of the parties in the commercial context of the Contract would be that
    the provision served two purposes: first, to provide for, and quantify, automatic liability
    for damages in the event of delay; second, to limit Dobler’s overall liability for late
    Mrs Justice O’Farrell DBE
    Approved Judgment
    E v D
    completion to a specific percentage of the final contract sum. The clear intention of the
    parties was that Dobler’s liability for delay damages would be so limited.
  98. Therefore, if, contrary to my finding above, the liquidated damages provision in clause
    2.32.1 were void and/or unenforceable, EWB would be entitled to claim general
    damages but subject to the overall cap on liability of 7%.
    Conclusion
  99. For the reasons set out above, the answers to the issues are as follows:
    i) The liquidated damages provision in clause 2.32.1 is valid and enforceable.
    ii) If, contrary to the finding on issue i), the liquidated damages provision were
    void or unenforceable, EWB would be entitled to claim general damages for
    delay, subject to an overall cap of 7% of the final Trade Contract Sum, as a
    limitation of liability provision.
  100. Following hand down of this judgment, the hearing will be adjourned to a date to be
    fixed for the purpose of any consequential matters, including any applications for
    permission to appeal, and any time limits are extended until such hearing or further
    order.

This article was originally written and published on the internet by Bailii. This document (and any information accessed through links in this document) is provided for information purposes only and does not constitute legal advice. Professional legal advice should be obtained before taking or refraining from any action as a result of the contents of this document. BDAS specialise in: providing contract advice, resolving construction disputes, managing construction claims & adjudications and will give you competitive, independent advice tailored to your specific construction problems. If you could benefit from this please call Jon now on 07795 231 231 or email: Enquiry@BDAS.co