Pay less notices must be issued against the relevant application for payment.

This was a part 8 application by Advance for a declaration concerning the validity of its Pay less Notice (PLN) in respect of two payment applications (AFP24 and AFP 25) by ENISCA. An adjudicator decided Advance did not issue a valid PLN against AFP 24 and awarded ENISCA £2.7m. In the court application it was […]

Enforcement of Adjudicators Decision when no payment decided.

In Level 1 Raised Flooring v JM Construction (SW) [1] the TCC declined to enforce an adjudicator’s decision on the basis that no payment had in fact been awarded in the adjudicator’s decision. This case is a reminder of the importance of drafting the notice of adjudication so it is clear what issues the adjudicator […]

Mandatory adjudication clauses before court action.

In Lancashire Schools SPC Phase 2 Ltd v Lendlease Construction (Europe) Ltd [2024] EWHC 37 (TCC) a local authority failed in its application to have the claim against it stayed or struck out on the basis of non-compliance with a contractual dispute resolution mechanism.  The relevant building contract (the Contract) provided for adjudication before proceedings, […]

Construction Contracts Exclusion Order 20

On 1 October 2022, the Construction Contracts (England) Exclusion Order 2022 comes into force.  The Order will exclude contracts within the water and sewerage infrastructure industries “for the delivery of a direct procurement for customers project”, or “DPC”, from the Part 2 provisions contained in the Housing Grants, Construction and Regeneration Act 1996 (the “Act”).  […]

Part 7 & Part 8 procedures; Adj deciding on basis not argued by parties.

Mallino Development Ltd v Essex Demolition Contractors Ltd [2022] EWHC 1418 (TCC) (10 June 2022) started as a Part 8 procedure (i.e. an unconventional court procedure for an issue which does not involve a substantial dispute of fact) seeking to circumvent the enforcement of the second of two adjudication decisions, eventually tried under the Part […]

Decision on issue not given – due to lack of evidence vs decision on issue that it fails – due to lack of proof, effect on subsequent adjudications.

A recent decision of the Scottish Court of Session has considered whether the failure to prove a delay damages claim in one adjudication prevented the claimant from renewing the claim in a subsequent adjudication. In finding that the claim could not be re-adjudicated, the Court sought to distinguish a previous TCC decision in England where […]

Notices of Adj, omission of parts of works, Adj must give parties opportunity to comment if important elements of his Dec have not been argued by the parties.

IN THE HIGH COURT OF JUSTICEBUSINESS AND PROPERTY COURTS IN NEWCASTLETECHNOLOGY AND CONSTRUCTION COURT (KBD) The Moot Hall, Castle Garth,Newcastle upon Tyne, NE1 1RQ 06/12/2023 B e f o r e : HH JUDGE DAVIS-WHITE KC(SITTING AS A JUDGE OF THE KING’S BENCH DIVISION)____________________Between: ILUMINESIA LIMITED(t/a ALTEREGO FACADES) Claimant – and – RFL FACADES LIMITED […]

Adjudicator power to award interest under Late Payment Act 1998.

The adjudicator has no free-standing power to award interest and paragraph 20(c) of the Scheme for Construction Contracts 1998 (if it applies to the adjudication) does not give him one (Carillion v Devonport). The adjudicator only has power to award interest if that issue has been referred to him or the parties have agreed it falls […]